Surface Mount Technology (SMT) lines represent the single largest capital investment on any Electronics Manufacturing Services (EMS) shop floor. A single high-speed SMT line can cost ₹5-7 crore in CAPEX and utilisation of SMT line decides profitabiilty of the EMS organisation.
Here’s the brutal reality:
Capacity lost on an SMT line cannot be recovered.
Unlike post-SMT operations where you can add manpower or overtime, SMT downtime = permanent revenue loss.
Why SMT Scheduling is Mission-Critical
Every EMS planner faces three core constraints when scheduling SMT production.
- Product Cycle time (How much can be produced in an hour )
2. Changeover time
3. Material avaialbiltity
For high-mix EMS (20-30+ models/week), this becomes mathematically impossible to solve manually using Excel spreadsheets.
The High-Mix SMT Scheduling Nightmare
Manual planning challenges:
- No visibility into theoretical SMT capacity per model
- Changeover times ignored (30-90 mins between models)
- Material shortages discovered only when line stops
- Priority customer orders crashing the schedule mid-week
- No “what-if” scenarios for unexpected delays
Result: SMT utilization drops to 20-30% instead of target 85-90%.
Typical Weekly Loss from Poor SMT Scheduling:
• SMT Idle Time: ₹12-18 lakhs/week
• Changeover Inefficiency: ₹3-5 lakhs/week
• Rush Production Costs: ₹4-6 lakhs/week
-------------------------------------------
**TOTAL: ₹20-30 lakhs/week lost**
The Solution: Rated Capacity-Based SMT Scheduling
Step 1: Benchmark Your SMT Reality
Measure & Document:
├── Cycle time per model (Cpk validated)
├── Changeover time (feeder/nozzle swaps)
├── Planned maintenance downtime
└── New product qualification time
Step 2: Build Theoretical Capacity
Example: Based on the optimised program, we can calculate machine cycle time
• Model A - 200 UPH
• Model B - 120 UPH
Alternately, we can actually run a product and calcuate the cycle time for each model. Add an efficiecy factor of 85% to ignore minor stoppages.
Step 3: Sequence Using Constraints
Priority Matrix:
1. Customer Delivery Date (Critical)
2. Kit Readiness (100% complete)
3. Changeover Efficiency (Common feeders, Nozzle groups)
4. Capacity Fit (Don't overload line)
Introducing the SMT Scheduler Tool
I’ve built a production-ready Excel tool that solves high-mix SMT scheduling in 5 minutes:
What Planners Input:
• Product Model & Description
• Cycle time per board (minutes)
• Changeover time (model-specific)
• Expected delays (trials, qual, etc.)
🎯 What the Tool Delivers:
• Optimal production sequence
• Start/finish times for each kit
• Multi-line capacity balancing
• Shopfloor-ready schedule PDF
Download Your FREE SMT Scheduler Today
Perfect for:
- High-mix EMS (20-100 models/week)
- 1-36 SMT lines
- Multiple shifts
- Dynamic customer priorities